The project, which was funded by the Swedish International Development Cooperation Agency "Sida" was divided to two stages, and included the rehabilitation and reconstruction of Hosh Hanania; a building that was collapsed in 1999 during its rehabilitation.
The rehabilitation of Hosh Hanania provided 534 working days; the first phase was implemented between the 2nd of April 2011 and the 2nd of May 2011, and the second phase was implemented between the 3rd of August 2011 and the 1st of February 2012 and provided 4,929 working days